Islington - Upper Street

The consultation period for this section of Bus Route 38 ended on 31st July 2008

Executive Summary

The public consultation phase for Route 38 proposes a package of improvements along the Route 38 corridor. In total there are 13 consultation areas and this report presents the results of the recently completed consultation exercise for the Upper Street section of the route.

This consultation report specifically refers to nine proposals along Upper Street as detailed below, and can be seen in the consultation leaflet, Appendix A:

Upper Street Map

Of the 6,092 leaflets distributed for the Upper Street section of Route 38, a total of 604 questionnaires were returned; this is a 9.9% response rate.

Other media were also used to seek feedback including public exhibitions, a newspaper advertisement and the project website.

In addition to the leaflet questionnaires returned, a total of three letters, 14 emails and 14 website responses, 17 telephone calls and an additional 17 comments received from the public exhibitions from residents, interest groups, businesses and other organisations.

The duration of the consultation period was six weeks, commencing on Thursday 19th June and ending on Thursday 31st July, 2008. However, Atkins accepted leaflets until Wednesday 5th August 2008.

Respondents of the questionnaire were asked to indicate whether or not they supported the proposals for Upper Street. The overall questionnaire responses as shown in the figure overleaf indicate the following:

Following consultation results, it is recommended that of the nine proposals, seven are to be taken forward without modifications. Proposal E is recommended, subject to further information being provided to the public, whilst Proposal G is under review. This is summarised in the table below.

Proposal Recommendation

Proposal

Description

Recommendation

A

Relocate pedestrian crossing facilities at Liverpool Road junction to the northern approach.

Recommended

B

Relocate existing loading bay on the west side near Liverpool Road a few metres south.

Recommended

C

New 'shared surface' loading bays with extended hours of operation – only possible with Proposal E.

Recommended - only if Proposal E is progressed

D

Widening of pedestrian footway on the east side of Upper Street between Duncan Street and Islington Green – only possible with Proposal E.

Recommended - only if Proposal E is progressed

E

Removal of one lane of traffic southbound

Recommended - Provisional Recommendation subject to further traffic analysis following completion of junction works*

F

Widening of southbound bus lane to four metres – only possible with Proposal E

Recommended - only if Proposal E is progressed

G

Bus lane operational hours extended to 24 hours a day

Under Review

H

Relocate pedestrian crossing facilities at Berners Road junction to the southern approach in order to accommodate the new pedestrian crossing north of Islington Green junction.

Recommended

I

Existing loading bay to be shortened by four metres to accommodate a new pedestrian crossing.

Recommended

* As the construction sequence will involve the junction changes being carried out first, and the footway widening last, there will be an opportunity to assess the actual traffic flows that arise following the junction changes (it is proposed junction changes that bring about the improved traffic flow). These observed flows can then be fed back into the traffic model to double check the initial assessment that the traffic lane removal will work.

Response Overview

Respondents of the questionnaire were asked to indicate whether or not they supported changes to pedestrian facilities, parking and loading, general traffic, bus lanes and public space. The overall questionnaire responses indicate the following:

The Figure below shows an overview of the responses to all questions asked.

Overview of Responses to all Proposals

Overview of Responses to all Proposals

From the Figure above, it was noted that:

Of the nine proposals, eight received more support than opposition;

What Next?

The next steps in the process are as follows:

If you want further details about these proposals, please download a copy of the
Street consultation leaflet.

These leaflets have been distributed to all properties in the following area and to local and statutory groups, emergency services and ward councillors.

Some of these documents are Adobe Acrobat PDF documents. You may need to download the free Acrobat Reader to view them